June 29th, 2018 + November 7th, 2018 - Haul-Out and splashing
November 2018 - various repairs
May
- November 2018 - Replacing the Teak deck
March 28th – April 23rd, 2018 - Overview of our work during the stay in Cayman Islands
23.4. Mo
- Interchanged cables at autopilot (mixed-up)
- Autopilot quit function after engine stop. First tests: fuse ok, 12V at control panel ok
22.4. So
- Shortened Aries rudder pole
- Attached side panel
21.4. Sa
- Sewed side panel and added grommets
18.4. Mi
- Detected leak at Propane gas bottles
- Detected clogged drain after demounting Propane gas compartment drain hose. Cleaned drain and mounted new hose.
16.4.
- Connected 120V temporary; connected cable from shore power inlet to Inverter
14.4.
- Wired cable from shore power inlet to main power distribution cabinet
13.4.
- Installed new Autopilot Unit, preformed first tests
11.4.
- Demounted Diesel lift pump, exchanged gasket, sealed und installed pump. Comparison with old unit shows membrane damage
8.3.
- Drilled hole in water tank lid for fitting. Installed fitting
5.4.
- Started to sew side panel for cockpit (wind protection)
4.4.
- Sewed diver flag
2.4.
- Autopilot: measured control and supply voltage; deinstalled mechanic and opened it up => signal-wheel is worn down and electric motor is not working
February 25th – March 26th, 2018 - Overview of our work during the stay in Kuba
20.3.
- Connected cockpit speaker
19.3.
- Build water filter (prefilter and activated carbon) for external water supply
18.3.
- Serviced JIB sheet block
- Music System: installed radio amplifier, condensator and salon speaker
- Soldered cable and installed lamp in salon
12.3.
- Cut frayed ropes with hot cutter
10.3.
- Tensioned V-belt and checked oil level
9.3.
- Cut Dinghy Transom for lowering outboarder
8.3.
- Exchanged fresh water pump, the old one didn’t suck anymore
3.3.
- Build anchor snubber and attached
- Repaired not working boat light
- Repaired Diesel leak at the tank vent hose
Older pictures in the archive